What a window and door change order is for
Window jobs change at two moments: before the order goes in, when owners add or drop openings, and on install day, when the old units come out. A signed change order at either moment, with photos for anything found in the wall, keeps the order right and the final invoice free of surprises.
What to put on a window and door change order
- What changed and when.
- Openings added or dropped.
- Repairs found at tear-out, with photos.
- The new total and its effect on the order.
- Owner's signature.
A worked example
Before ordering, the owner adds the garage side window and drops the storm door. On install day, the kitchen sill turns out to be rotten.
| Line | Qty | Unit | Price |
|---|---|---|---|
| Add replacement window, garage side | 1 | each | Your price |
| Credit: storm door | -1 | each | Your price |
| Sill and frame rot repair, kitchen | 6 | ft | Your price |
Changes to units must be signed before the order goes in. After that, a change may mean a new order and a new lead time.
Line items window and door installers use
| Line item | Unit | How to write it |
|---|---|---|
| Replacement window, insert install | each | Size, frame material, glass package and grid. |
| Replacement window, full frame | each | Tear-out to the rough opening; new trim inside and out. |
| Entry door, prehung | each | Slab material, glass, sidelites and hardware. |
| Storm door | each | Style and closer. |
| Sliding patio door | each | Width, panels and screen. |
| Interior door, prehung | each | Swing and casing. |
| Exterior capping, aluminum | each | Per opening; color to match. |
| Interior trim and stool | each | Per opening; paint or stain grade. |
| Sill and frame rot repair | ft | Priced if found when the old unit comes out. |
| Egress window and well | each | Cutting, well and code requirements; permit. |
| Disposal of old units | each | Per opening. |
| Permit | each | Where the town requires one. |
Terms and deposit language for window and door
- Deposit. A deposit at signing pays for the units, which are made to the measured size and cannot be returned. Check your state's limits on home improvement deposits.
- Payment. Balance due on install day once every opening is finished and the owner has opened and locked each unit.
- Warranty. The manufacturer warrants the units. You warrant the install: leaks at the opening and operation problems caused by how it was set. Say for how long.
- Lead times run from the order date, not the signing date, and are set by the manufacturer.
- Rot found when an old unit comes out is repaired at the per foot price on this estimate, with photos.
- Blinds, curtains and alarm sensors on old units are the owner's to remove and reinstall unless listed.
How to fill it in
- Put in the original estimate number and amount.
- Write what changed in the reason box, plainly.
- Add the new work; type a minus quantity for any credit.
- Fill in the days added.
- Print it for a signature on site, or send it from Koira to sign by phone.
Free tools for window and door
The same change order for other trades: appliance repair, auto detailing, carpentry, carpet cleaning, chimney, house cleaning, commercial cleaning, concrete, deck, drywall, duct cleaning, electrical, fence, flooring, garage door, general contractor, glass, gutter, handyman, holiday lighting, home inspection, hood cleaning, hvac, insulation, irrigation, junk removal, landscaping, lawn care, locksmith, masonry, moving, painting, pest control, plumbing, pool service, pressure washing, property maintenance, remodeling, restoration, roofing, security system, septic, siding, snow removal, solar, tile, tree service, water treatment, waterproofing, window cleaning.